Evaluate the Relationships Between Durations And/Or Costs
The Risk Sensitivity chart evaluates the relationship between durations and/or costs by creating a scatter chart showing their interaction.
To run the Risk Sensitivity chart, complete the following steps:
- Select the S3 // Risk tab.
- In the Views group, click .
- On the Risk Sensitivity configuration screen, select X and Y axis activities and values for each activity to view their relationship.
- Click Analyze to create the Risk Sensitivity chart.
Parent Topic: Risk Chart Procedures